PennDOT Roadwork Schedule- Week of March 31- April 6

Posted on Friday March 31, 2017

The following roadwork is scheduled for this week on Interstate 81.

Baseball is back: Please note there will be traffic issues at Davis Street, I-81 and Montage Mountain Road, Moosic, at the beginning and end of the games.

Opening  Day is Monday, April 10, 2017 at 7 p.m.   The Railriders will have home games on Monday, April 10, starting at 7:05 p.m.; Tuesday, April 11, starting at 6:35 p.m. Wednesday, April 12, starting 6:35 p.m.; Thursday, April 13, starting at 6:35 p.m.; Friday, April 14, starting at 6:35 p.m.; Saturday, April 15, starting at 4:05 p.m.; and  Sunday, April 16, starting at 1:05 p.m.

Short Term Projects

This work has been rescheduled.  There will be night work moving guiderail damage repair operation on I-81 Southbound scheduled for Monday, April 3,  Tuesday, April 4  and Wednesday, April 5 from 8 p.m. to 4 a.m. from Exit 194  (Clarks Summit) to Exit (178)  Avoca.

Long Term Projects

Lackawanna County I-81 Southbound- Beginning at Exit 202 (Fleetville – Tompkinsville) to Exit 199 (Scott). A private contractor for PennDOT continues work on a $9,982,000 project to replace bridge decks on Interstate 81 South between Exit 199 (Scott) and Exit 202 (Fleetville – Tompkinsville). There will be single lane traffic from Exit 202 to 199 from April through November this year. The On Ramp to SR 81 Southbound from SR 107 at Fleetville/Tompkinsville will be Closed from April 17, 2017 through August 2017. A detour will take traffic onto I-81 Northbound to Exit 206 (Lenoxville) to turn around and come back Southbound.

The locations of the bridges to be replaced are as follows:
Spring 2017 – Southbound:
Two bridges at Exit 202 (Fleetville – Tompkinsville)
Bridge at Exit 201 (East Benton)
Bridge at Exit 199 (Scott)
In addition to the replacement of the bridge decks, there will be paving of the shoulders and bridge approach work.

I-81, Jenkins – I-81 Bridges Jenkins/Pittston, Rehabilitation and improvement of 81 North and South between Exit 170 (Bear Creek/Wilkes-Barre) and Exit 178 (Avoca/Wilkes-Barre Scranton Airport), construction of four single span steel plate girder bridges, removal of existing bridges, milling, superpave asphalt wearing course, overhead sign structures, temporary cross overs, drainage, guiderail, temporary concrete barrier, erosion and sediment control measures, pavement markers, temporary traffic control, signing, temporary excavation and support, and other miscellaneous construction, Let January 2014, NTP March 2014, To Be Completed December 2017.

Starting mid-April I-81 Southbound Traffic pattern changes will include a split about 1,000 feet north of Exit 175 (Pittston). Crews use the split pattern so they can do work in the middle lane while still maintaining two lanes of traffic on I-81. Motorists will need to stay in their lanes as they travel through the construction area. This split will be in place until  October 2017.

I-81, Exit 175 to SR 315 northbound at Oak Street-Armstrong Drive widening project will be completed by the end of June 2017.  The will allow for three lanes of traffic to come off the exit ramp.